Facilities Requirements — Integration Readiness
This document defines site / facilities prerequisites required for bring-up, commissioning, and SAT.
It is used to prevent late blockers by making utilities, safety, and network constraints explicit and testable.
1) Scope
Facilities readiness includes:
- Power & grounding
- Network / VLAN / security approvals
- Utilities (CDA, exhaust, vacuum, DI water — as applicable)
- Safety infrastructure (E-stops, interlocks, LOTO, signage)
- Environmental constraints (space, clearances, vibration/noise)
2) Facility prerequisites (minimum for Move-in / Install)
2.1 Power
- Voltage / phase: ________
- Breaker rating: ________
- Grounding / bonding verified: [ ] Yes [ ] No
- Power quality requirements (if any): ________
- Acceptance check:
2.2 Network / VLAN / Security
- VLAN requested: ________
- Ports / drops available at tool location: [ ] Yes [ ] No
- Security approval complete: [ ] Yes [ ] No
- Acceptance check:
2.3 Space / Access / Handling
- Footprint + keep-out zones confirmed: [ ] Yes [ ] No
- Rigging path cleared: [ ] Yes [ ] No
- Crane/forklift schedule reserved (if needed): [ ] Yes [ ] No
3) Utilities (apply as needed)
Mark N/A if not required by your system.
3.1 CDA (Clean Dry Air)
- Pressure range: ____
- Flow requirement: ____
- Acceptance check: [ ] Regulator installed [ ] Leak check complete
3.2 Exhaust
- Exhaust type: ____ (house / dedicated)
- Flow requirement: ____
- Acceptance check: [ ] Hood connected [ ] Airflow verified
3.3 Vacuum
- Vacuum requirement: ____
- Acceptance check: [ ] Pump available [ ] Stable vacuum achieved
3.4 DI Water / Cooling
- DI water: [ ] Required [ ] N/A
- Cooling water: [ ] Required [ ] N/A
- Acceptance check: [ ] Flow verified [ ] Temperature within spec
4) Safety & EHS prerequisites (minimum for Power-on)
- LOTO plan reviewed: [ ] Yes [ ] No
- Emergency stops tested: [ ] Yes [ ] No
- Door/guard interlocks tested: [ ] Yes [ ] No
- Safety signage and access controls: [ ] Yes [ ] No
- Acceptance check:
5) Acceptance criteria by phase
Move-in / Install Exit Criteria
Commissioning Exit Criteria
SAT Exit Criteria
6) Evidence expectations
Evidence examples:
- Photos of panel labeling + utility hookups
- Network approval ticket ID
- Voltage/pressure/flow readings
- Test logs showing safety chain signals (door open, E-stop)
Link evidence files under: docs/evidence/