| Project start: 2026-01-02 | Duration (days): 125 |
Tasks (sorted by earliest start): T001 ES: 0 EF: 5 LS: 0 LF: 5 Slack: 0 CRITICAL Finalize Charter T010 ES: 5 EF: 19 LS: 5 LF: 19 Slack: 0 CRITICAL Requirements Baseline T030 ES: 5 EF: 20 LS: 34 LF: 49 Slack: 29 Site Survey & Utilities Plan T020 ES: 19 EF: 34 LS: 34 LF: 49 Slack: 15 ICD v0.1 Draft T040 ES: 19 EF: 21 LS: 33 LF: 35 Slack: 14 Long-Lead Orders Placed T050 ES: 19 EF: 35 LS: 19 LF: 35 Slack: 0 CRITICAL Design Freeze (HW) T090 ES: 20 EF: 45 LS: 49 LF: 74 Slack: 29 Facilities Readiness Minimum T060 ES: 34 EF: 44 LS: 49 LF: 59 Slack: 15 Controls Release Lock Candidate T070 ES: 35 EF: 59 LS: 35 LF: 59 Slack: 0 CRITICAL Build Assembly (EVT) T080 ES: 59 EF: 74 LS: 59 LF: 74 Slack: 0 CRITICAL FAT Execute T100 ES: 74 EF: 85 LS: 74 LF: 85 Slack: 0 CRITICAL Move-in & Install T110 ES: 85 EF:100 LS: 85 LF:100 Slack: 0 CRITICAL SAT/Commissioning T120 ES:100 EF:125 LS:100 LF:125 Slack: 0 CRITICAL Qualification Run
Critical path tasks: T001 -> T010 -> T050 -> T070 -> T080 -> T100 -> T110 -> T120