RAID Log (Template)

One line per item. Keep it current. Review every week.

ID Type (R/A/I/D) Title Domain Severity Owner Due date Status Mitigation / Next step Link / Evidence
I-001 Issue Facilities readiness blocked (0%) due to network/VLAN approval Facilities High 2026-01-10 Open Escalate IT ticket; define temporary isolated network workaround; update readiness checklist weekly docs/evidence/readiness_score_output.md
R-002 Risk Controls readiness at 50% may cause churn during integration if versions not locked Controls Med 2026-02-10 Open Establish “FAT Release Lock” by Controls Release Lock Candidate date; require change control for any post-lock changes docs/evidence/readiness_score_output.md
R-003 Risk Design Freeze (HW) is on the critical path; late changes will directly slip Build Assembly (EVT) Hardware High 2026-02-05 Open Enforce change control; prioritize closure of open design issues; daily burn-down on freeze blockers docs/evidence/critical_path_output.md
R-004 Risk Long-lead parts / supplier delivery slip may compress EVT build window and jeopardize FAT start HW/Supplier High 2026-01-16 Open Confirm supplier commit dates; dual-source where feasible; prepare expedite triggers + alternates data/sample/ims_tasks.csv
I-005 Issue FAT Execute is critical-path; test readiness gaps could delay FAT start or reduce evidence quality Test Med 2026-02-25 Open Finalize FAT plan + staffing; pre-stage instruments; define “minimum evidence” checklist for FAT exit docs/evidence/critical_path_output.md
R-006 Risk Move-in & Install is critical-path; facilities “minimum readiness” may not align with install window Facilities/Ops High 2026-03-15 Open Weekly joint readiness review (Facilities+Ops); lock install window; contingency install plan if readiness slips docs/evidence/critical_path_output.md
R-007 Risk SAT/Commissioning on critical path; safety/EHS signoff timing could block power-on EHS/Safety Med 2026-03-25 Open Pre-review LOTO + interlock validation plan; schedule EHS walkdown early; create SAT safety checklist evidence pack docs/gates/checklists/G5_SAT_COMMISSIONING_CHECKLIST.md
D-008 Decision Proceed with “release lock” policy for FAT to prevent late churn (PLC/FW/HMI + IO map) Controls Med 2026-02-10 Proposed Publish release lock rules; create CR template usage; communicate rollback + retest scope docs/raids/DECISION_LOG.md