Week of: 2026-01-01
Program health (RAG): 🟡
| Milestone | Plan date | Forecast date | Delta | Owner | Notes | |—|—:|—:|—:|—|—| | Finalize Charter (T001) | 2026-01-06 | 2026-01-06 | 0d | PM | Sponsor signoff + publish cadence/RAID | | Requirements Baseline (T010) | 2026-01-20 | 2026-01-20 | 0d | Eng Lead | Freeze v0.1 requirements + RTM baseline | | Site Survey & Utilities Plan (T030) | 2026-01-22 | 2026-01-22 | 0d | Facilities Lead | Confirm power/network/utilities; capture constraints | | ICD v0.1 Draft (T020) | 2026-01-24 | 2026-01-24 | 0d | Controls Lead | Initial IO map + protocols for integration | | Long-Lead Orders Placed (T040) | 2026-01-16 | 2026-01-16 | 0d | SCM | Confirm supplier commit dates + expedite triggers | | Design Freeze (HW) (T050) | 2026-02-05 | 2026-02-05 | 0d | HW Lead | Change control mandatory after freeze |
| Blocker | Domain | Owner | ETA | Escalation needed | |—|—|—|—:|—| | Network/VLAN approval not complete (drives Facilities readiness = 0%) | Facilities | Facilities Lead | 2026-01-10 | Yes — IT escalation if not approved by ETA | | Controls version churn risk before FAT (needs release lock policy before T080) | Controls | Controls Lead | 2026-02-01 | Yes — approve “FAT release lock” decision | | Supplier lead time uncertainty for long-lead components (risk to T070 EVT build start) | HW/Supplier | SCM | 2026-01-16 | Monitor — trigger expedite/alternate sourcing if slip forecasted |
| Risk | Severity | Mitigation | Owner | Due | |—|—|—|—|—:| | Facilities network/VLAN approval delays site readiness minimum | High | Escalate IT ticket; pre-approve compliant temporary isolated network workaround if needed; track weekly | Facilities Lead | 2026-01-10 | | Long-lead parts slip build start (impacts EVT build on critical path) | High | Confirm supplier capacity + commit dates; dual source where feasible; expedite triggers | SCM | 2026-01-16 | | Controls release churn causes late integration defects / retest | Medium | Define FAT release lock; allow changes only via change control + defined retest scope | Controls Lead | 2026-02-10 | | Safety interlock validation expands scope late (SAT/commissioning impacts) | Medium | Pre-test interlock logic; align EHS signoff checklist early; schedule walkdown | EHS Lead | 2026-01-20 | | Install window conflict / site access limitations | Medium | Lock install window; pre-stage tooling; align contractors + site services | Ops | 2026-03-10 |
docs/evidence/critical_path_output.mddocs/evidence/readiness_score_output.md